Bay Area Rail Plan

Scorecard · checked October 15, 2026

The 2007 Bay Area Regional Rail Plan. What got built?

In September 2007 the Bay Area agreed a 50-year plan for its trains: BART, Caltrain, high-speed rail, and new lines around the Bay. Nineteen years on, here is every main project, with what happened and a source for each.

Built and running (8)

Partly built (3)

Under construction (4)

Still on paper (5)

Dropped (3)

How this was checked

The project list comes from the plan's final report (MTC, September 2007), mainly the phasing table in Chapter 8. Each status was checked on October 15, 2026 against agency pages, board minutes and news reports, linked on each card. A few dates rely on Wikipedia, cross-checked with news coverage.

Not yet checked, so left off the scorecard: BART Silicon Valley – San José airport connector; BART Oakland fourth track / lower-level platforms; West Oakland Capitol Corridor station + people mover; North Bay (Napa–Solano–SMART) passenger rail; eBART extension to Tracy.

Spotted something out of date? Write to hello@bayarearailplan.info.